Electrical Project
Customer | Eaton |
End User | Microsoft |
Sites | Virginia, Washington, & Wyoming |
Product | Custom designed Deposit on Base Enclosure (DOBE) for MV Switchgear |
Challenge | Short lead time to place buildings on-site |
Solution | AMR PEMCO devised a floor-less building (DOBE) with the same features as a typical AMR PEMCO building. The DOBE was delivered the same day as the switchgear for setup on the concrete pad. This eliminated shipping equipment to AMR PEMCO for install in a traditional equipment building. This solution allowed the project to succeed on time and under budget. |